As of 2026-07-24. Everything under “Fixed in this pass” is committed, and the published report is rendered from the corrected data.
This is the record of what was consciously deferred in D4 and why. The reader-facing caveats that bear on interpreting the numbers live on the Coverage & Limitations page. Nothing below changes the headline medians, which are robust to these tails. Companion pages: Coverage & Limitations and Date Sourcing & Provenance.
Fixed in this pass
- CE register-vs-document decisions — prefer the authoritative BLM/DOE register when a document-text CE decision disagrees by >~2 years (~650 CE decisions corrected).
- Negative-duration ordering — reclassified to
invalid_orderat source (05 / 05c normalizer) with an assertion in 08; the old downstream stopgap was removed. - 06 LLM cache-replay — on a cache hit, script 06 now re-applies the stored adjudication from
timeline_api_adjudications.parquet(no API call), so a regeneratedproject_datesrestores the full LLM layer deterministically for $0. - Fossil-EA reporting — corrected the “84% = well-abandonment” error (84% is the register-anchoring share; well-abandonment is 53%), and added a second “Fossil (doc-anchored)” row to Figure 6 (~5-month median) as the more defensible review-length view.
- Data-quality caveats + this note — split the report’s caveats into “resolved this pass” vs “deferred” and added this deferred-items note.
- CE/EA universe reconciliation (2026-07-15) —
05_select_dates.py’s universe reconciliation, previously EIS-only, now covers all process types: the 628 CE + 66 EA zero-candidate projects appear asmissing_bothstubs, so coverage denominators equal the full 61,881-project inventory. Applied to the published parquet additively (--reconcile-only): all pre-existing rows are byte-identical; no date, duration, or median changed. - EIS methodological note — the Phase-1-gap / FEIS-proxy explanation at the bottom of this page.
- LLM adjudication cache re-keyed on project+slot+model (2026-07-22, todo #49). The adjudication replay in
06_adjudicate_llm.pypreviously re-applied a cached answer only on an exact prompt-hash match (SHA-1 of the full prompt text, which embeds the candidate-packet composition), so a from-scratch re-selection that re-formed different packets dropped the CE LLM layer entirely (the “layered artifact” problem, formerly deferred below). 06 now falls back to a project + slot (initiation/decision) + model key: exact prompt-hash stays the primary path, and on a miss it re-applies the most-recent successful selection for that project+slot+model, resolved against the current candidates bycandidate_id(a stable content hash). Fallback design chosen over a full re-key because the fix needs no cache-file migration — theselected_initiation_candidate_id/selected_decision_candidate_idcolumns already carry the answer — and it is strictly a superset safety net that can only add a re-application the exact key would have missed, never change one it would have hit. Evidence (both read-only against canonical data; the cache file andtimeline_project_dates.parquetwere preserved byte-for-byte): (1) replaying the fallback map against the publishedtimeline_project_dates.parquetreproduces 14,778 / 14,778api_adjudicationslots — 8,306 CE (6,551 init + 5,869 decision) + 797 EA + 1,227 EIS projects — with 0 date changes; (2) an end-to-end run of the real patched_apply_adjudication_resultsagainst a simulated fresh re-selection (everyapi_adjudicationslot cleared, exact prompt-hash forced to miss so only the fallback fires) restored 7,858/7,858 initiation + 6,920/6,920 decision slots to their published values, all taggedapi_adjudication, 0 mismatches. CE complete-timeline coverage (54.7%) now survives a fresh re-selection instead of collapsing to 45.7%.
Deferred — documented, not in active development
None of the items below are being actively worked. They are recorded so the underlying issue is understood and can be picked up later if a future pass warrants it — not because any of them is queued or in progress.
- EIS decision-coverage gap (biggest open issue; investigated and closed 2026-07-14). EIS complete coverage is ~32% (valid-order complete timelines), below Phase 1’s ~48% for decarb EIS. This is not in active development. We did build and test a targeted selection-only fix in an isolated worktree (route month-granularity dates on ROD/FEIS documents to the LLM; widen the FEIS cover-date regex, both in script 05); it recovered only ~57 projects (~+1.5 pts), which confirmed the real bottleneck is upstream candidate generation, not selection. The worktree was discarded — nothing was promoted and the published data was untouched. The full explanation of why EIS is lower than Phase 1 and why the recovery is hard is in the methodological note at the bottom of this page; a real fix would be a heavy Phase-2.1 re-extraction, only if someone decides to invest in it.
Lower-priority / diagnostic (no deliverable-number impact)
- #8 VALIDATION-GOLD (medium). Build a disjoint, held-out project-level gold set (~180 projects, hand-verified from source docs) to produce an honest end-to-end precision/recall. Deferred because it is effortful (labeling) and adds an accuracy statistic without changing any reported number. The report carries the honest caveat (“end-to-end accuracy not yet formally validated against a held-out gold set”). Current project-level gold (
timeline_gold_projects.parquet) is ~76% contaminated (overlaps ranker-train + 05c injection), so it is not a clean accuracy measure — hence the caveat rather than a stated number. - #10 YEAR-ANCHOR (medium). Add a
nepa_case_yearsanity-anchor flag to selection/QA (flag/down-rank a selected date that sits >~2 years from the case-number year, e.g.DOI-BLM-ID-B010-2022-0032→ 2022). Deferred: it is a diagnostic flag that does not change the selected dates; requires a case-year-derivation step first; and the main thing it would catch (historical-citation initiations) is already documented below. - #15 GOLD-CLEANUP (low). Delete the retired candidate-level gold apparatus (
labeling/gold-builder scripts +data/analysis/timeline/gold/+output/deliverable04/gold/candidate-level artifacts). KEEP the project-leveltimeline_gold_projects.parquetused by07_validate.py. Pure housekeeping — deferred, and to be done carefully (confirm the exact file list first) if/when #8 is picked up. - Cushman Hydroelectric (EIS-0456) outlier — manually verified genuine (2026-07-24). The 18.1-year span flagged
suspect_error(“early LLM-picked initiation (verify)”) was verified against source text: the 1992-11-02 initiation is FERC’s notice of intent to prepare the DEIS for the same EIS-0456 relicensing action that the 2010-11-29 DOE-register ROD concludes (the FEIS’s own §1.3 procedural history quotes the NOI). The flag’s caution was warranted but the date is correct; the project is retained outside the case-study prose by editorial choice. - CE long-duration outliers (historical-citation initiations). ~106 CE reviews (0.4%) show 13–45-year “durations” because the extractor selected a decades-old citation (original grant, covering PEIS, prior plan) as the initiation instead of the recent application/renewal date. The candidate-level
historical_gap_candidateflag already exists but is under-weighted in ranking (plus a ~9-row bug where LLM adjudication overrode a correct ranker date). The CE median is 20 days with or without these rows. A fix (strongerhistorical_gap_candidatepenalty in 05) is deferred because it is a global CE-ranking change — it would require a full re-run + verification for a 0.4%, no-headline-impact gain. These rows are flaggedsuspect_errorin10_outliers.R. - The published parquet is a layered artifact — RESOLVED 2026-07-22 (todo #49), see “Fixed in this pass” above.
timeline_project_dates.parquetis the product of the July-14 selection plus LLM adjudications applied across the June 2026 runs. Originally the adjudication cache re-applied only by prompt hash (project + exact candidate-packet composition + model), so a cached adjudication re-applied only if a fresh run re-formed the identical packet; empirically 0 of 8,306 CEapi_adjudication-sourced dates re-formed on a from-scratch05 → 05c → 06re-run (EA 797/797 and EIS 1,227/1,227 re-formed completely), which would have dropped CE complete coverage from 54.7% to 45.7%.06_adjudicate_llm.pynow carries a project+slot+model fallback that re-applies the stored selection when the prompt hash misses, resolved against the current candidates bycandidate_id; a validation replay reproduced all 14,778api_adjudicationslots with 0 changes and confirmed CE coverage survives a fresh re-selection (evidence in “Fixed in this pass”). Regeneration guidance (still holds): treat the published parquet plustimeline_api_adjudications.parquetas the reproducibility root; use05_select_dates.py --reconcile-onlyfor additive universe fixes. The remaining residual is thatcandidate_iditself is only stable while extraction (02/03) is unchanged — a full re-extraction that shifts page boundaries could still alter a few ids, but the fallback is strictly more robust than the old prompt-hash key (it needs only the one selected candidate to survive, not the whole packet to re-form). - Smaller register/document CE decision disagreements. Sub-2-year disagreements are left to the ranker (the >2-year, decade-scale ones were fixed this pass).
- Post-FRA CE durations. Post-FRA CE runs modestly longer than pre-FRA (median ~37 vs ~19 days; ~1.9× shrinking to ~1.3× once proxy rows are excluded). The residual is spread across date sources, not a single bug. NOTE: the old “43 vs 1,005 days, n≈208” figure was from a stale pre-fix build (10× less coverage) and does not reproduce on current data.
Deleted (not doing)
- #9 CALIBRATION-SPLIT. 04b calibrates the classifier confidence in-sample (on the frozen test split). A dedicated out-of-sample calibration split was deleted from scope — it affects only internal confidence scores (not the selected dates), moves report numbers, breaks comparability, and can trigger LLM re-routing. Revisit only if calibration is specifically challenged.
- #13 BUCKET3-INIT. ~959 projects produced no candidates at retrieval (scanned/corrupt PDFs, no extractable text). Deleted from scope — not recoverable without OCR reprocessing; ~1.5% of the universe.
Methodological note: why EIS decision coverage is lower than Phase 1, and why the EIS dates are a best guess
Phase 1 reported ~48% complete timelines for decarbonization EIS; Phase 2 reaches ~32% (valid-order complete) for all-energy EIS on a roughly 5× larger universe. This is a genuine difference, but it is explained by scope plus a structural data limitation — not a pipeline regression — and we confirmed the cause empirically (2026-07-14) before accepting it.
The structural cause. An EIS “decision” is a Record of Decision (ROD), a separate document that in NEPATEC 2.0 is usually absent — only ~18% of EIS have a ROD in the corpus. Where there is no ROD, the pipeline falls back to the Final-EIS publication date as a month-granularity proxy for the decision (imputed to the 15th of the month). So a large share of the EIS decision dates we do report are best-guess proxies (FEIS publication ≈ decision), not authoritative ROD signature dates. That is why EIS coverage is both lower and lower-confidence than CE or EA.
Why the gap can’t be cheaply closed (tested and abandoned 2026-07-14). We investigated the 2,388 EIS that lacked a decision — 836 of which have a ROD/FEIS document in the corpus — and found the bottleneck is candidate generation, not selection:
- 33% (275 of 836) have no decision-date candidate extracted at all. The ROD/FEIS cover date was never captured by retrieval/extraction, so there is nothing for the selection step to pick.
- ~60% were already sent to the LLM, which returned no usable decision. Typically a month-only cover date (“June 2015”) is extracted with the identifying “Final Environmental Impact Statement” title on a different page, so the date ranks below the top-3 candidate packets and the model never sees it.
- A targeted selection-only fix (routing month-on-ROD/FEIS-document dates to the LLM; widening the FEIS cover-date regex) recovered only ~57 projects (~+1.5 pts) — confirming selection is not the wall.
What a real fix would take (Phase 2.1). Re-pull the FEIS/ROD cover pages to generate candidates for the ~275 with none, and improve how month cover dates are ranked into the LLM packets. That is a heavy re-extraction over the 5.5 GB EIS page corpus plus additional LLM spend — out of scope for this deliverable.
Bottom line. Present EIS coverage as-is, with the caveat that a large share of EIS decisions are Final-EIS-publication proxies (month-granularity), and that the shortfall versus Phase 1 is a corpus / ROD-availability limitation, not an extraction error. The EIS timelines are the best available estimate given what NEPATEC 2.0 contains.